Supply Type on Shop Order Created from Project Deliverables.

  • Sep 8, 2022 5:41 PM UTC
  • 2 replies
  • 181 views

Forum|alt.badge.img+13

It seems that when I create a Shop Order within Project Deliverables that the system automatically sets the Supply Type for the Material to Project Inventory.  Is there a way to define the parts or setup the system so that we can use standard inventory for the shop order material?

 

Thank you

Patrick

2 replies

Forum|alt.badge.img+2
  • Do Gooder (Employee)
  • Jul 2, 2024 2:09 AM UTC

Hi, 

You can use the supply option MRP for the materials if you are referring to the standard inventory. 

Regards,

Sasika


AveTonitM
Hero (Partner)
Forum|alt.badge.img+11
  • Hero (Partner)
  • Jan 27, 2025 1:42 PM UTC

Can You configure the system so that ‘Project MRP’ would be the default supply option for project material demands? How does the system set the supply option when creating a new material demand to the project deliverable?