Hello Community,
I have created a SOW Production from a SOW Estimated where Sales Contract was Connected.
Then I entered some work recording and tried to updated the sales contract from SOW Production. As per solution it should create AFP for the progress. But i an unable to sync the progress in Sales Contract. The sales contract is in Active status along with the revision & items.
I was able to update the Project Forecast, Project EAC, Project Material Plan , Project Resource Plan from the SOW.
Does anyone know how to sync the progress to sales contract and sub contract?