Revenue based on Activity milestone

  • Nov 13, 2026 2:55 PM UTC
  • 1 reply
  • 17 views

Forum|alt.badge.img+11

We have a scenario where a project revenue must be taken based on reaching an activity milestone. The activity has a weighting % (example: 20%) and can be change based on the project need.

Is it possible to do this in IFS Cloud Projects? 

1 reply

Forum|alt.badge.img+5
  • Do Gooder (Employee)
  • Nov 18, 2026 10:56 PM UTC

Hi ​@FPayab,

 

Yes, but not by putting a weight % on the activity. The standard way is Event Based revenue recognition on the financial project, with one event per milestone.

 

Setup

1.On the Financial Project, set the Revenue Recognition Method to Event Based. This method only works with the Manual POC method.

2.In the Events section, add one event for each milestone.

3.Give each event its share of the project revenue as its estimated revenue. For example, 20% of a 1,000,000 project means 200,000 on that event. If you turn on Apply Margin Consistently, each event's estimated cost is calculated from the project margin, so you only have to maintain the revenue.

4.When the milestone is reached, complete the event (or update its POC), then run revenue recognition.
Changing the weighting Update the event's estimated revenue. All events together still have to match the project's estimated revenue and cost. So if one milestone goes from 20% to 25%, take the extra 5% from another event.

 

Things to know

*An event isn't linked to a project activity. Finishing the milestone activity won't update the event, so someone has to complete it by hand. Making it automatic takes a customization, and people have done this with custom fields. IFS confirmed it here: https://community.ifs.com/finance-financials-42/event-based-revenue-recognition-end-to-end-flow-53429

*According to my research, the other option is setting the POC method to Project Progress and using Template Progress or Manual progress on the milestone activities. The problem is that an activity's weight in project progress is its share of planned (or baseline) cost, not a percent you set. You'd only get 20% if that activity carries 20% of the planned cost. If you want to set the weights yourself, Event Based fits better.

 

Hope this helps,

Gleb