Resource Groups are entered ONSHORE and replicated to OFFSHORE.
However, connection to Project Cost and cost element are NOT replicated. Any Idea on this?
Best answer by Peshala Fernando
View originalResource Groups are entered ONSHORE and replicated to OFFSHORE.
However, connection to Project Cost and cost element are NOT replicated. Any Idea on this?
Best answer by Peshala Fernando
View originalHi Bhakthi,
As per the user guide regarding replication I found that Resource cost elements should be replicated from onshore to offshore. But when it comes to project Cost it is not a replication entity currently.
Hence for future developments you can add an idea with regard of project cost
Regards,
Peshala.