Solved

Resource Group – Details not in sync (O&G Extension)

  • 17 September 2021
  • 1 reply
  • 67 views

Userlevel 3
Badge +3

Resource Groups are entered ONSHORE and replicated to OFFSHORE.

However, connection to Project Cost and cost element are NOT replicated. Any Idea on this?

icon

Best answer by Peshala Fernando 17 September 2021, 07:05

View original

1 reply

Userlevel 5
Badge +9

Hi Bhakthi,

 

As per the user guide regarding replication I found that Resource cost elements should be replicated from onshore to offshore. But when it comes to project Cost it is not a replication entity currently.

 

Hence for future developments you can add an idea with regard of project cost

 

 

Regards,

Peshala.

Reply