Dear colleagues,
We are on IFS Cloud 22R2 SU13 and it happens that Resource Analysis page shows negative values as the resource requirements for some days. We have resource requirements from Project Activities only. I do not understand how the resource requirements can be negative.
Values in Planned Hours, Planned Minutes fields in Resource Activity Load Detail page are also negative. I am attaching couple of screenshots.
Can anybody explain?
Thank you very much.
Best Regards
Antonin