Project Transactions Invoiceability set as Delayed Invoicing Still Posted


Forum|alt.badge.img+8

Issue: Project Transactions Invoicability is set as “Delayed Invoicing”, still project transactions were considered for “invoicing” and invoice status is “Paid Posted”. What can be the reason or Is it a bug? 

 

 

Thanks & Regards

Pratik Shah

Best answer by Johan Lagerström

Hi @pratik.b.shah

It was recently found that Delayed Invoicing transactions were incorrectly included on the invoice when using the Project Transactions Review page in the Aurena client. Could this be the issue you are seeing?

A correction for that specific issue is included in Update 23 for Apps 10, and as a workaround the filter section can be used to filter out only Invoiceable transactions before invoicing.

Kind regards,
Johan

 

View original

Forum|alt.badge.img+9

Hi @pratik.b.shah

It was recently found that Delayed Invoicing transactions were incorrectly included on the invoice when using the Project Transactions Review page in the Aurena client. Could this be the issue you are seeing?

A correction for that specific issue is included in Update 23 for Apps 10, and as a workaround the filter section can be used to filter out only Invoiceable transactions before invoicing.

Kind regards,
Johan

 


Forum|alt.badge.img+1
  • Do Gooder (Customer)
  • December 19, 2024

Hi Pratik,

 

I am using IFS10 UPD9.

My project is set for ‘Not Invoiceable’, still MCPR are transactions getting created as ‘Invoiceable’.

Is this also resolved in Update 23 ?

I have attached the document for your reference.


Reply