Hi @CM6 ,
The problem for the system is that, whilst demands are easy to summarise, e.g. Project CM19102022 wants 3 x Kelly123 on the 01/12/2022, The supply could be from all over the place, One could come from Project CM19102022 stock, another could come from general non-project inventory and a third could come from Project XYZ that has shareability in place with the demanding project.
All this would be difficult to display on a single overview screen, especially as it could all change as soon as you run PMRP again. It would be simpler in a Make to Stock environment but in any industry where supply is contingent on a lot of factors it would be very confusing to try and summarise all the supply on to a single screen
Gareth Williams