Hi everybody,
In project MRP do I have to define PNG groups? Can I run PMRP without define PNG groups?
After I run PMRP where can I see the results?
Thank you
Hi everybody,
In project MRP do I have to define PNG groups? Can I run PMRP without define PNG groups?
After I run PMRP where can I see the results?
Thank you
HI Amy, This question is from 2 years ago but better late than never.
You can run PMRP without using PNG.
You can switch off the Create Project PNG Automatically flag on PNG Default Settings so that the system does not automatically create them
Then run the ‘Perform Project MRP per Activity’ process
The results will be visible on the Material Requirements Planning screens that are all filterable by project
Hopefully you got the answers you needed before now