Does any understand the rules around Project Exceptions and how to clear them especially the two that affect your cost:
- Resource Planning
- Planned Value Exceeded
Is there any documentation that explain these, have been looking at the Planned Value Exceeded and just presumed that it was that my Planned Cost was lower that my Committed Cost + Used cost. But on the example I looked at my planned cost was fine. So looked in more detail and discovered that Baseline cost was lower than my Committed + Used Cost, adding my activity to the Baseline cleared my exception.
Thanks
Mark