What is the difference between project cash forecast and budgeted forecast? What is the purpose of creating a project cash forecast?
Solved
Project Cash Forecast
Best answer by Ieva Rituma
Users manually associate the cash plan to the project cash forecast.
Time delay for invoices and supply chain elements are calculated automatically based on payment terms. If a project cash forecast is copied from project forecast spreading, then it’s possible to apply the time delay at the cost element level as part of basic data. Alternatively, users can do the cash in/out spreading manually.