Project Budget control for Project Cost/Time Registration

  • July 11, 2023
  • 2 replies
  • 234 views

Abdul
Superhero (Partner)
Forum|alt.badge.img+20
  • Superhero (Partner)
  • 543 replies

Hello Everyone,

 

I am unable to configure Project Budget for Project Time Registration and Project Cost Registration (Personal and Non-Personal Cost). 

Is Project budget controls Procurement related transactions only? Or am I missing some sort of setup.

 

Regards

Best answer by EqeMithuV

Hi @Abdul

Yes, you can only control project procurement transactions against the project budget. It would be very much helpful if we would have the option to control budget on other project transactions as well.

You can post this as an idea in community and hopeful IFS may considered this in future releases.

Regards,

Mithun K V

2 replies

Forum|alt.badge.img+18
  • Superhero (Partner)
  • 392 replies
  • Answer
  • July 11, 2023

Hi @Abdul

Yes, you can only control project procurement transactions against the project budget. It would be very much helpful if we would have the option to control budget on other project transactions as well.

You can post this as an idea in community and hopeful IFS may considered this in future releases.

Regards,

Mithun K V


Cameron Brittain
Sidekick (Employee)
Forum|alt.badge.img+4
  • Sidekick (Employee)
  • 9 replies
  • March 11, 2024

Do we know IFS R&D are looking at this ?