Project Baseline Cost summary has included on cancelled activity

  • 1 June 2023
  • 1 reply
  • 42 views

Badge +1

We have a project where cost breakdown is like mentioned above. When we checked the baseline there’s an extra $26,826.58 in cost that doesn’t show under project connections. That extra $26,826.58 has come from an Activity which is in Cancelled state. 

 

Can a cancelled Activity have a baseline cost? 

There is no planned/estimated cost.  I tried to add it on the estimate tab, rebaseline, delete, then rebaseline but I can’t because the activity is cancelled.  Simply rebaselining does not fix it.


1 reply

Userlevel 6
Badge +17

Hi @Miyuru Gimhana ,

This issue should resolve if you perform Set Baseline again for the project. I tested this and it works for me.

Hope this helps!!

Regards,

Mithun K V