When entering Project Activities using the following numbering structure, it automatically places the order by grouping the numbers as shown, resulting in 1.10 being listed before 1.2 etc. Is there a way to prevent this?
1.1
1.10
1.11
1.2
1.3
I want the sequence to be as follows:
1.1
1.2
1.3
1.10
1.11
Great Suggestion!
“Idea” for this lives here »
@VanCarolK While I understand the context behind this idea, it is quite difficult because the Activity id is a alpha numerical value. When such values sort this is the outcome. Making the activity id is a number would solve the issue but it is not a solution.
In most implementations, the best option is to avoid this patten but stick to 10, 20, 30 or 101, 102, 103