When entering Project Activities using the following numbering structure, it automatically places the order by grouping the numbers as shown, resulting in 1.10 being listed before 1.2 etc.  Is there a way to prevent this?  

1.1

1.10

1.11

1.2

1.3

I want the sequence to be as follows:

1.1

1.2

1.3

1.10

1.11

 

2 replies

Seth M
Do Gooder (Customer)
Forum|alt.badge.img+2
  • Do Gooder (Customer)
  • 7 replies
  • November 7, 2024
VanCarolK wrote:

When entering Project Activities using the following numbering structure, it automatically places the order by grouping the numbers as shown, resulting in 1.10 being listed before 1.2 etc.  Is there a way to prevent this?  

1.1

1.10

1.11

1.2

1.3

I want the sequence to be as follows:

1.1

1.2

1.3

1.10

1.11

 

Great Suggestion!
“Idea” for this lives here » 

https://community.ifs.com/ideas/make-project-activity-id-sequence-friendly-53854

 


Buddhika Kurera
Superhero (Employee)
Forum|alt.badge.img+15
  • Superhero (Employee)
  • 388 replies
  • November 21, 2024

@VanCarolK While I understand the context behind this idea, it is quite difficult because the Activity id is a alpha numerical value. When such values sort this is the outcome. Making the activity id is a number would solve the issue but it is not a solution.

In most implementations, the best option is to avoid this patten but stick to 10, 20, 30 or 101, 102, 103

Just thinking loud here.