If we create a Project Purchase that has a minimum order qty and then more demand is created, its not looking at the surplus supply and IFS creates another purchase requisition to purchase more.
Example:
Project demand: 10
PO X 50 ( Minimum order qty)
Surplus: = 40
New project demand x 10
PMRP creates another Purchase requisition x 50