Question

Planned cost on project vs part unit cost


Forum|alt.badge.img+3

Hi All,

I’ve an issue that I’m not able to understand: i systematically have a gap between the part unit cost and the panned cost on a project. The cost of raw materials (prod structure) is missing

 

In this example we can constat the issue between a customer order and a project:

But i have the same problem withshop orders and misc demands,

 

Does anyone has an idea about this issue?

 

Thanks in advance :)

 

Antoine

3 replies

Tharindu Illangasinghe
Superhero (Partner)
Forum|alt.badge.img+15

Hi @antoine.vignon,

 

Has this been sorted now ?

If not, could you please tell me what is the “Supply Code” of the Customer Order Line you are referring to ? Cost fetched from the CO Line depends on that.


Forum|alt.badge.img+3
  • Author
  • Do Gooder (Partner)
  • 5 replies
  • August 6, 2024

Hi @Tharindu Illangasinghe  thanks for your answer :)

I get the same result with supply code = “Shop order” or “Project Inventory” i do not see any difference :-S

 


Tharindu Illangasinghe
Superhero (Partner)
Forum|alt.badge.img+15

Ok, then the Planned Cost should get retrieved from Part Costings.

Could you drop a screenshot of the Part Cost of Cost Set 1 of this Inventory Part ? Also, is it a manufactured or purchased part ?


Reply