I am trying to add a part number in a certain configuration structure in IFS 10 but I keep getting this error, “Phase in Date of this component conflicts with parent revision date range.” The part number has a phase in date of 06/24/2024 and the phase in date of the configuration structure I want to put it in has a phase in date of 08/03/2023 and does not have a phase out date. Not sure why it won’t let me add the part number 

 

In order to be used in Rev 4 of FD PRE-D, the component must have a Phase In prior to or equal to 8/3/2023.


Do you know then how to change the phase in date of the part number to be prior to or equal to Rev 4?

 


Actually, I just figured it out, thank you!!

 