Skip to main content
Solved

on screen of project navigator early start date of each activity changed automatically what is reason ?

  • 11 June 2024
  • 1 reply
  • 34 views

Hi Experts,

on screen of project navigator early start date of each activity changed automatically i.e 03-03-2024 changed with 01-01-2016. what is reason why this was change automatically. is there any impact from other screen/form please suggest solution.

 

 

Regards,

Waqar 

1 reply

Userlevel 4
Badge +8

Hello,

The Early Start Date is the planned start date of the activity.

If the activity is part of a project schedule and the critical path method is utilized, Early Start is the earliest date the activity can start based on the schedule logic, the present date and constraints.

 

Regards.

Reply