Hi Experts,

on screen of project navigator early start date of each activity changed automatically i.e 03-03-2024 changed with 01-01-2016. what is reason why this was change automatically. is there any impact from other screen/form please suggest solution.

 

 

Regards,

Waqar 

icon

Best answer by TimeMarBou 11 June 2024, 14:36

View original

1 reply

Userlevel 4
Badge +8

Hello,

The Early Start Date is the planned start date of the activity.

If the activity is part of a project schedule and the critical path method is utilized, Early Start is the earliest date the activity can start based on the schedule logic, the present date and constraints.

 