Hi @MCIPSTEV,
What does the Earliest Activity Start Date you set when creating the project? This date is the earliest activity start date in the target project. All the project activity dates copied from the source project, will be set relative to this date in the target project.
Hi,
I agree with the statement regarding the project activity dates. However, the planned finish date entered (01/09/2025) disappears in the created project and is not taken into account.
We need to ensure that the entered planned finish date is correctly set on the project. Additionally, we have added an action to set the planned finish date for all tasks to the entered planned finish date plus 90 days. This is necessary because once the planned finish date of a task has passed, it becomes impossible to create a purchase order for that task.