One of our customers is facing an issue with modifying (Cancel) the Project Forecast after the status is set to "Approved" and the budget is activated. Once the budget becomes active, the status button is no longer visible.

Is there a possible workaround to allow changes to the Project Forecast in this situation?

Thank you!

Navoda

Best answer by Abdul

Hi ​@Navoda.Nuwangi,

Please create new revision for your forecast and do desire changes before activating the new revision. 

Changes are not allowed for Project Forecast once status set to Active.

 

Regards 

Abdul Rehman

1 reply

Abdul
Superhero (Partner)
Forum|alt.badge.img+20
  • Superhero (Partner)
  • 538 replies
  • Answer
  • June 3, 2025

Hi ​@Navoda.Nuwangi,

Please create new revision for your forecast and do desire changes before activating the new revision. 

Changes are not allowed for Project Forecast once status set to Active.

 