Question

Limit creation of MTR (Material Transfert Requisition)

  • 5 March 2024
  • 1 reply
  • 32 views

Badge +2

Hello everyone,

I’m looking for some information about “Material Transfer Requisition”.

In our system, Material Transfer Requisition are causing a lot of problem: they prevent us from receiving shop orders, some receptions are blocked, ect…

More surprising, some requests transfer items from MRP to PMRP :

 

 

And then from an activity to another :

 

 

So I'm looking for a way to limit the creation of MTR, if anyone has any ideas, thank you for your help !

Have a nice day !


1 reply

Badge +4

Hi Tom,

 

Did you check the settings in the planned netting group window for the project? In this window you have the setting if the MTR should be created for the project. 

Defaults for these settings are in the window: Project MRP Basic Data - PNG Default Settings.

In the online help there is a page called “Project Material Requirements Planning” that contains a general description.

Regards Alex

Reply