A resource group has four employees connected. All employees have 8 hour schedule per day. But the total numbers of hours per day of the resource group also shows 8. Shouldn’t it be 32 hours? It does not get updated although ‘Calculate Resource Capacity’ is run. How to get this corrected?

Individual hours per day. Four individuals set as this.

 

Resource group also shows only 8 hours per day

 

Hi,

A couple of things you could check:

  • Is the Capacity Calculation Base of the resource group set to Individuals?
  • Are the resources in the group set to 100% utilisation for that group?

Hope this helps?

Kind regards,
Johan

 


Hi Johan,

Thank you very much for sharing the possible causes for the issue. The setting mentioned second was missing and now it works fine.

Appreciate your help.

 

Best Regards,

Anne.