Two related issues:
1. When a user that is not in a user group refreshes project connections, all customer order connections are removed.
2. When a user that is in a user group refreshes project connections to restore this, only connections of active projects are restored.
Test Plan
• Login as User JARNO/jarno (Any user)
• User JARNO is removed from all user groups in company P10.
• Created a work task from Work order in activity sequence 100221678
• RMB and navigated to prepare WO window and under work task tab enter new record with duration. Released the Work task.
• RMB the line and report time in
• In CO information tab entered the customer and navigate to Report in
• RMB the header and created an Invoice preview for the work order. After approving the invoice CO has been created (CO: J33333510)
• Navigate to Project ID: PF-SPIE and review the activity
• You will notice planned revenue is not visible
• Now log in from Jackie and refresh project connections
• You will notice Planned revenue is visible in the activity
• Again, if you login from user JARNO (Any user) and refresh project connections planned revenue will be removed
Please help to find a solution or advise.