Community,
How we could stop a project to be reported in Time Registration?
will change Report Code Valid To date work?

Community,
How we could stop a project to be reported in Time Registration?
will change Report Code Valid To date work?
Hi
Yes, you are on right place. Set Report Code Valid To date for any past date to stop time registration for activity.
Regards
Abdul Rehman
I am wondering if we could close the project, so that the LOV of project activities in Time Registration will not show up?
Though Project closure would take time, and better close the Activity first to stop time regiration instantly. Let finance team work on Project closure as per SoP.
Hi
Further to the previous comment, please note that it is sufficient to set the Activity to the Completed status. This will prevent further time reporting (and also prevents initiating further other cost on the activity), while still letting you finalise any other outstanding work, e.g. cost accounting, sending a final invoice etc.
Hope this helps.
Kind regards,
Johan
your comment makes very much sense to me. appreciated.