How to setup dependencies on activities with start and finish dates
Dear all,
do you know a way to setup dependencies to have the start and finish date of an activity equal to the start and finish date of another?
In the example below, i need to have start and finish date of activity 02-60-30_ equal to activity 02-60-20_:
The idea is to only move the activity 02-60-20_ when needed and have the activity 02-60-30_ updated in consequence.
Thanks a lot for your help :)
Page 1 / 1
Hi,
in IFS this is currently not possible. you can make a start to start relation and a finish to finish relation, but that is not the same. In IFS that does not influence the duration of the activity.
Looks like you want a Hammock Activity like P6 can do.
So you could integrate with P6 and schedule there, or make a small CRIM item that does this for you.
The scheduling is rather simple ricght? the hammock activity has a planned start = planned start of the source, and a planned finish = planned finish of the source.
You would need a Custom Menu Item to trigger a small script to do this for you, after you scheduled the rest of the project in IFS
Regards Erik
Hi Erik,
thanks for your very quick answer. I also though about a Custom Menu while waiting for a Primavera integegration but i wanted to be sure that there was no other option.
Thanks a lot for your support
I think you should be able to do that using a couple of dependencies.
Create 2 dependencies between 2 activities in Gantt
And RMB on each line and set up the settings as “START-TO-START” & “FINISH-TO-FINISH”.
Hope this helps.
Hi Dasuni,
thanks a lot for your answer .
I’m trying to run your advice, my setup is the following:
unfortunatelly, when i expend the main activity …
… the dependent activty is not updated :
Did i make something wrong?
Thanks for your feedback
@RECOFR
Check if both activities have the same “Total Work Days”. One seem to have less work days
Hi Dasuni,
here is what i set, dates and work days are identical:
And here is what the system does when i tried to extend the start date of the main activity:
As you can observe:
the start date of the main activity is back to its initial state
the finish date of the main activity moved to the future
the finish date of the dependent activity didn’t change