how to add the same line with different start/end date for activity and cost and sub project in project forecast?

  • April 2, 2026
  • 1 reply
  • 14 views

Forum|alt.badge.img+8

hello

I want to create a project forecast for 12 months for the same sub project and activity and cost element like below picture,

I create one line and copy paste to have different start/end date, it will have error message pop-up, how can I make it happen.

.Look forward your reply soon. 

Thanks

Susan

1 reply

Abdul
Superhero (Partner)
Forum|alt.badge.img+20
  • Superhero (Partner)
  • April 3, 2026

Hi ​@Susan Su,

It is a logical error, and not possible to create more than one line for the same combination.

You need to use Spread Profile functionality to distribute the amount into different period.

Please refer to the link below, ​@Buddhika Kurera has explained the functionality in detail.

Project Spread Profile functionality in Project Forecasts | IFS Community

 

Regards

Abdul Rehman