Hi IFS-experts,
I am experience something strange when connecting a resource forecast to a project resource. On the Project Forecast the ETC value is 0 and, on the Resource Forecast the ETC value is also 0. When I make the connection between the Project Forecast and Resource Forecast the ETC value is recalculated to -99.382.
My expectation was that it would be the same as the ETC in Resource Forecast and Project Forecast. I am trying to understand how the logic is working in IFS. If someone can enlighten my knowledge about how this should be working, then I would be very glad about that.