Hi Community,

Please kindly advise on how to resolve this error message on the screenshot below. 

 

Hi Meshfemi,

Have you completed all of the following steps?

  • Set a duration
  • Planned the start date on the Work Task
  • Planned the finish date on the Work Task
  • Added a Resource Demand line
  • Ensured the Work Task is at "Released" status or higher
  • Ensured the Work Order is "Released"
  • Assigned the work to the Resource
  • Accepted the work

After completing these steps, the assignment seems to work fine for me.


 

 