When Transferring Resource Planning from the Forecast to the Project, using Transfer to Resource Planning,only the Activities in Planned and Released statuses in Sub Projects (which has activities with mixed statues Planned, Released, Completed) are updated.
The following warning message pops up to confirm it. It is possible to ReOpen, Completed Activities and then transfer the resource planning, if required. Otherwise only the activities in the above mentioned statuses are modified.