Diffrence MRP vs. P-MRP

  • March 6, 2024
  • 3 replies
  • 211 views

Forum|alt.badge.img+6
  • Do Gooder (Employee)
  • 19 replies

Hi people, can anybody tell me what are the general differences between MRP vs P-MRP qith respect to material demand by an Project activity. Thx in advance...

3 replies

ATSI
Do Gooder (Partner)
Forum|alt.badge.img+4
  • Do Gooder (Partner)
  • 12 replies
  • March 6, 2024

Without remembering much details, I think P-MRP (Project MRP) considers only demands and supply that are connected to project activities (that has project id and activity sequence). Otherwise most of the functionality is the same, I think.


Forum|alt.badge.img+3
  • Do Gooder (Employee)
  • 3 replies
  • March 6, 2024

MRP and PMRP are both very similar. They user data from Masters, Supply, Demand and Product Structures (BOMS) to calculate a purchasing and Production Plan for Project and Standard Inventory.

Some key differences are:

>PMRP does not create Supplier Schedules or Production Schedules and does not see any demand that is not Project Connected.

>A Planned Netting Group (PNG) is used by PMRP to move supply to where it is most needed by creating Material Transfer Requisitions

>PMRP does not plan to use Alternate Components where MRP may.


Forum|alt.badge.img+6
  • Author
  • Do Gooder (Employee)
  • 19 replies
  • March 7, 2024

Hi folks,

 

thx for your replies!