Hello,

I have an activity that I want to delete that has a baseline.  When I try, i get an error that “The Activity is used by 1 rows in another object (Project Baseline Detail).

I thought we used to have a selection that said to “exclude from project baseline” but in 21R2, I don’t see that selection.

How do I go about deleting an activity if it has a baseline?

Thank you

Patrick

4 replies

Forum|alt.badge.img+2
  • Do Gooder
  • 4 replies
  • June 16, 2022

were you able to delete the activity? I have the same problem


Forum|alt.badge.img+11
  • Author
  • Hero (Employee)
  • 120 replies
  • June 17, 2022

Hello,

 

I haven’t gotten a  response on this question.  I’m really not sure how RnD expects us to be able to do this.  

Try deleting your estimates, set a new baseline, and then try to delete the Activity.  

Please let us know if that worked.

Patrick


Forum|alt.badge.img+1
  • Do Gooder (Customer)
  • 1 reply
  • December 13, 2022

I am also having issues with deleting an activity because of the baseline.  Did you ever figure this out?

 


Forum|alt.badge.img
  • Do Gooder (Customer)
  • 2 replies
  • October 25, 2024

You cannot... Only cancel activity. Encourage you to vote for our improvement idea here which would help this issue.