Hello,

I have an activity that I want to delete that has a baseline.  When I try, i get an error that “The Activity is used by 1 rows in another object (Project Baseline Detail).

I thought we used to have a selection that said to “exclude from project baseline” but in 21R2, I don’t see that selection.

How do I go about deleting an activity if it has a baseline?

Thank you

Patrick

were you able to delete the activity? I have the same problem


Hello,

 

I haven’t gotten a  response on this question.  I’m really not sure how RnD expects us to be able to do this.  

Try deleting your estimates, set a new baseline, and then try to delete the Activity.  

Please let us know if that worked.

Patrick


I am also having issues with deleting an activity because of the baseline.  Did you ever figure this out?

 


You cannot... Only cancel activity. Encourage you to vote for our improvement idea here which would help this issue.

 Baseline - Possibility to delete project baseline | IFS Community