Hi All,
I have defined two TIME report codes in the application. One is for normal time and another one for overtime. Employees are reporting time against the project activities through the Time Registration window. While reporting time, employees enter 8hours under Normal Time report code and if any additional hours, it's report under Overtime report code. If the internal price of employee A is 100, I need cost to be reported as below.
If the report code is Normal Time, cost should be 100 x 1 = 100 per hour.
If the report code is Overtime, cost should be 100 x 1.5 = 150 per hour.
Simple my Internal Price criteria's are Employee and Report code. But I cannot define that combination in any of below screens. I cannot use Resource ID instead of Employee. Because my employees rate are differ from one to another even in same Resource Group.
Is there any standard functionality to fulfil this requirement?

Regards,
MalinG.