Question

Customer Order Line Connection

  • 11 April 2024
  • 3 replies
  • 31 views

Badge +1

I am getting the following error when trying to connect a line in Project Navigator.

 

Does anyone have a solution for this? 

 

 


3 replies

Userlevel 6
Badge +13

I don’t know about budget/planning code but “invalid time interval” on project is this Valid Until field in Financials/Project Accounting/Project

 

Might also be worth checking the planned finish date on the activity

 

 

Badge +1

Yes, that worked.

 

Thank you for the help!

Userlevel 6
Badge +13

You’re welcome!

Reply