Costs and hours progress disappears from project screen

  • November 22, 2023
  • 3 replies
  • 96 views

Forum|alt.badge.img+6

Hi,

We have noticed a strange behavior in project navigator. When we report hours both cost and hour progresses are reported. However during the day for some reasons progress is reduced to 0% although the activity is reported. Does anybody know what can cause the issue?

Best regards,

Bernadeta

3 replies

Forum|alt.badge.img+9

Hi @Bernadeta Woszczyna ,

That sounds somewhat similar to the issue discussed here: 

That particular issue only affected the 22R2 version of IFS Cloud though, and it looks like you are on Apps 10(?). I would suggest reporting it as a support issue so it can be investigated in more detail.

Kind regards,
Johan


Ushan Senarath
Hero (Employee)
Forum|alt.badge.img+11
  • Hero (Employee)
  • 45 replies
  • December 5, 2023

Hi @Bernadeta Woszczyna 

You may be able to use ‘Refresh Project Connections’ as a workaround.

This seems like an issue in the summary view and the progress might be correctly set in the connections level.

Best regards, Ushan

www.linkedin.com/in/ushan-senarath


Forum|alt.badge.img+6
  • Author
  • Do Gooder (Customer)
  • 10 replies
  • December 5, 2023

Hi,

Thank You All for your answers. We had already tried with Refresh Project Connections. The issue was solved for some hours and again it was back to 0% during the day. We are still monitoring  and trying to see what causes the issue.

 

Best regards,

Bernadeta