Complete a sales contract before final application

  • Sep 30, 2026 8:15 AM UTC
  • 3 replies
  • 24 views

Forum|alt.badge.img+2

Morning,

 

We are doing billing from sales contracts connected to a project. Our client PO is entered into revisions and items, we have found that users are able to close the sales contract before all applications are complete against the revisions and items. As per the standard docs: Complete Sales Contract, it seems this should not be possible. Are we missing some basic setup to prevent this or get a warning? 

 

Thanks

Sean 

3 replies

SNBLAVA
Sidekick (Customer)
Forum|alt.badge.img+6
  • Sidekick (Customer)
  • Oct 26, 2026 3:02 PM UTC

HI, i am curious to the responses on your question, because we got the same question about this. As far as we have noticed until now you will only get a warning message when you want to complete the sales contract: total of AFP must be equal to sales contract.

Kind regards

Lars


richardwoods
Do Gooder (Partner)
Forum|alt.badge.img+6
  • Do Gooder (Partner)
  • Nov 24, 2026 10:05 PM UTC

Short answer: the standard wording puts the application for payment rule on the second step, Close, rather than on Complete. A contract in Active status is moved to Completed once the work is done, and the check that every application is Fully Paid or Cancelled, and that the total paid covers the contract sales value, is made when you take the contract from Completed to Closed. So it is worth finding out which of the two your users are actually doing.

Why the two steps behave differently

Complete is the "work is done and the completion certificate has been received" step. It needs the contract in Active status, and afterwards you cannot create new revisions or change the contract. Applications for payment still can be created and processed after that, and any interim retention is released automatically. Close is the "all financial transactions are finished" step, and that is where the application for payment rule sits. The message behind it is the one saying there are applications for payment not in Fully Paid or Cancelled status. Lars has seen a warning about the total of the applications when completing, so your release may also check something at Complete; the Close rule is the one I would rely on.

A way to set it up around that

  • Check the status your users actually reach. On Sales Contracts (Contract Management, Sales Contract), look at the contracts you consider closed too early. If they sit in Completed, that would match the standard behaviour: Complete does not carry the application rule, and further applications can still be raised against it.
  • Make Complete a deliberate step. Before anyone runs Complete, have them review Monitor Contract Sales Value Summary for the contract. In the standard process that review sits just before Complete. For your set-up, where the client PO is split into revisions and items, a sensible routine is to compare the sales value of the active revision with what has been applied across its items.
  • Limit who can run it. For example, give the Complete command only to a contract manager role through your permission sets, and leave general users with read and edit rights on the contract.
  • Leave Close to the standard check. Finance can then close once every application is Fully Paid or Cancelled.

The awkward case

If a contract has been Closed by mistake, it is not lost. A Closed contract can be reopened from the More menu in the contract header (Reopen), so the Close step is recoverable, and it is a cheaper fix than trying to rebuild the application history.

Things to know

  • Retention does not have to be fully released to close; the Close step allows for that.
  • The total paid must be equal to or higher than the contract sales value, so a contract with part of the PO not yet applied for will not pass Close, but can still be Completed.
  • Application statuses to look at are Planned, Approved, Submitted, Certified, Partially Paid, Fully Paid and Cancelled; only the last two count for Close.

Worth a look: the IFS Cloud documentation topics Complete Sales Contract and Close Sales Contract, and the permission set side of the Complete command if you want to restrict it.

Which status do the contracts show when you find them closed too early, Completed or Closed? If it is Closed, the exact message (if any) users see when they close would help narrow it down.

Created with the help of Ask Olive.


SNBLAVA
Sidekick (Customer)
Forum|alt.badge.img+6
  • Sidekick (Customer)
  • Nov 25, 2026 8:42 AM UTC

Thank you Richard!