Question

Changing a Project group

  • 13 October 2021
  • 1 reply
  • 632 views

Userlevel 5
Badge +8

Can a Project Group be changed after approving the Project? Seems it cannot be directly changed from the Project setup parameters in Aurena


1 reply

Userlevel 5
Badge +8

After approving the project, the system automatically creates a Financial Project. This project can be viewed in the 'Financial Project' window. If you want to amend the Project Group, this can be done in the 'Financial Project' window and it will be reflected in the 'Project Setup Parameters' window.

Reply