Skip to main content

Hello, 

we want to add a planning item as Work Task in project deliverables (Engineering-->Project Deliverables-->Plan and Execute-->Project Deliverables Navigator-->Project Deliverables Design). It is not possible as you can see in the following screenshot: 

 

Error Work Task

We are able to add the other executions types without any problems. 

We added and checked the Basic Data for Work Task and Work orders without any success. 

Could somebody get us a hint why this is not possible in this installation? (Parameter, Basic Data, Permissions…) 

Thank you in advance!

Robert

Hi ​@Robert Gwosdz,

To overcome this issue, you should have PLADES & WO Components installed. The code checks whether you have those components. That is why you are getting this error.

 


Reply