Skip to main content
Solved

Bulk Copy Activities to a new Sub Project


Forum|alt.badge.img+3

Is it possible to copy multiple activities into another sub project in the same project or a different project? The option is available for single activity copy. We need to remove 10 activities from sub project 1 and copy it to sub project 2 under the same project. AS we have a lot it is time consuming to copy one by one. 

Best answer by desilvasachitha

Hi ​@Nim0910esh,

As far as I know, IFS is not designed to support shifting Object connections that brings in Cost and/or Revenue to a Project from a connected object using the “Copy Activity” functionality (In Scope and Schedules view).

It is not possible to transfer Cost and/or Revenue object connections (that brings in Planned Committed, Committed, Used and Actual Costs/Revenues) over to a new Activity due to two main reasons. 

a) ‘Activity Sequence’(Unique Identifier of a Project Activity) is used to establish a connection between the activity and the object in question (in your case a ‘Shop Order”).

Hence, it must be noted that even though one can copy and carry over a copy of ‘Activities’ themselves (together with Estimated Costs, planned cost if the driver is former and some other details including activity classes, connected tasks, miscellaneous demands, planned resources, and valid report codes), the original object connection/s against the source Activity is locked in from the respective Object’ side (In your case the Shop Order/s would still holds the Activity Sequence/s from previous Activity and/or Activities).

Moreover, this Activity Sequence is used in the voucher level when costs are posted from the external object, ensuring that these costs are posted in GL against the Project Code Part and under the correct project, sub project and respective activity. 

b) Moreover, if a user wants to manually change the ‘Activity Sequence’ from the external object end, it becomes problematic after the status of the said object/s gets promoted over a certain point. Where manually editing the ‘Activity Sequence’ (thereby attempting to change the Project connection that injects the cost and or revenue to project) on that Object is prevented by the system. 

Hope this helps. 

Cheers!
Sachitha D

View original
Did this topic help you find an answer to your question?

5 replies

PRODQ
Superhero (Customer)
Forum|alt.badge.img+17
  • Superhero (Customer)
  • 459 replies
  • March 14, 2025

You can change the Sub Project they’re connected to - if that’s what you were trying to achieve … ?  I think they have to be Planned status with no costs allocated

 

 

 

I’ve been able to select multiple activities and copy/paste using the standard function ...

 

Changing the Sub-project before saving…

Not sure if this is what you’re looking for?

 


Forum|alt.badge.img+3
  • Author
  • Do Gooder (Customer)
  • 9 replies
  • March 19, 2025

Hi Linda,

Appreciate your response. 

I wanted to know if there is a way to completely move all the details to a new sub project if already transactions are made. We few shop orders created and some other object connections. When you copy sub project or the activity it will only transfer few object connections but we loose the shop order connection details. So the costs will not reflect the full value where it sits in the old activity. 

 


desilvasachitha
Sidekick (Partner)
Forum|alt.badge.img+5
  • Sidekick (Partner)
  • 12 replies
  • Answer
  • March 19, 2025

Hi ​@Nim0910esh,

As far as I know, IFS is not designed to support shifting Object connections that brings in Cost and/or Revenue to a Project from a connected object using the “Copy Activity” functionality (In Scope and Schedules view).

It is not possible to transfer Cost and/or Revenue object connections (that brings in Planned Committed, Committed, Used and Actual Costs/Revenues) over to a new Activity due to two main reasons. 

a) ‘Activity Sequence’(Unique Identifier of a Project Activity) is used to establish a connection between the activity and the object in question (in your case a ‘Shop Order”).

Hence, it must be noted that even though one can copy and carry over a copy of ‘Activities’ themselves (together with Estimated Costs, planned cost if the driver is former and some other details including activity classes, connected tasks, miscellaneous demands, planned resources, and valid report codes), the original object connection/s against the source Activity is locked in from the respective Object’ side (In your case the Shop Order/s would still holds the Activity Sequence/s from previous Activity and/or Activities).

Moreover, this Activity Sequence is used in the voucher level when costs are posted from the external object, ensuring that these costs are posted in GL against the Project Code Part and under the correct project, sub project and respective activity. 

b) Moreover, if a user wants to manually change the ‘Activity Sequence’ from the external object end, it becomes problematic after the status of the said object/s gets promoted over a certain point. Where manually editing the ‘Activity Sequence’ (thereby attempting to change the Project connection that injects the cost and or revenue to project) on that Object is prevented by the system. 

Hope this helps. 

Cheers!
Sachitha D


PRODQ
Superhero (Customer)
Forum|alt.badge.img+17
  • Superhero (Customer)
  • 459 replies
  • March 20, 2025
Ni0910mesh wrote:

Hi Linda,

Appreciate your response. 

I wanted to know if there is a way to completely move all the details to a new sub project if already transactions are made. We few shop orders created and some other object connections. When you copy sub project or the activity it will only transfer few object connections but we loose the shop order connection details. So the costs will not reflect the full value where it sits in the old activity. 

 

As ​@desilvasachitha has outlined in detail, the Activity Sequence number is the unique identifier that connects the cost transactions to the particular Project/SubProject/Activity.  That ID is carried across all transactions from order creation to cost in the General Ledger so there is no mechanism for transferring an Activity and its associated costs to another Activity (and therefore Sequence).

 

You could have finance manually journal any existing costs from the “old” Activity Sequence to the “new” one and transfer any outstanding requirements but that’s particularly messy and not ideal.  

 


Forum|alt.badge.img+3
  • Author
  • Do Gooder (Customer)
  • 9 replies
  • March 24, 2025

Thank you ​@PRODQ  & ​@desilvasachitha  for your valuable information. It make sense and my question is fully answered I suppose. Thank you both of you!

We should be cautious when connecting activities into various objects.  


Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings