Actual Start Date of Activity is set automatically upon PO release

  • July 3, 2024
  • 1 reply
  • 74 views

When releasing a connected PO on a Project, a committed cost is shown as PO value but no Object Progress (It is 0%).

 

However, Actual Start Date of the activity is fetched automatically when PO is released.

 

Is that possible? Or is there a way to stop setting Actual Start date automatically when PO is released?

 

1 reply

Forum|alt.badge.img+9
  • Hero (Employee)
  • 86 replies
  • July 22, 2024

Hi,

I had the same issue when integrating to Primavera, as far as I know you cannot change this behavior.

But it would be good to get this solved in some way, fir example by having a setting that changes this behavior. Being able to select between Release PO and Receive PO line, to set the Actual start date?

If you have a good idea for this then you could post it on Share Your Ideas | IFS Community

Regards Erik