Activity Project: default early start

  • 4 July 2024
  • 2 replies
  • 21 views

Is it possible to define, by configuration, the early start in an Activity Project? When you create a new Activity in a Project, this field is filled with sysdate automatically.

My customer wants that this field is filled in with the project planned start and not with sysdate.

 

 

Thank you in advance.

Best regards

Sergio.

2 replies

Userlevel 7
Badge +18

@CedSergiG I think the only way to handle this is through a custom event., Once the activity is saved, the event could run and update the Early Start field with the Project Planned Start Date. 

Badge +4

Thank you Marcel. I thought about a solution like that, but before implementing a CRIM I wanted to make sure that the standard application does not allow to set that field.