Hi everyone,
In IFS, project budget control is enabled, but it appears that budget validation is performed at the cost-element level rather than the activity level.
For example, an activity has an estimated cost of KWD 1,000 under BM-CIV, but a Project Supply Request using BM-MEC can still create commitments exceeding the total activity budget.

My questions are:
- Is there a standard IFS configuration to enforce budget control at the activity level across all cost elements?
- If not, is a custom event or extension required to validate the total activity estimate when creating a Project Supply Request?
Any guidance or experience with similar scenarios would be appreciated.
Thanks!