Community,
below shop order work center R2 got 2 machines. each machine can produce 8 PCS per day (8hrs/day). I have below shop order is 16 PCS. We expect APB could assign 2 resources so that this SO can be completed in one day. But APB failed to do so, this SO is to be completed in 2 days, and only one resource is assigned. Where we missed in settings?
Work Center R2 is Finite Capacity, capacity is 16hrs/day.