Skip to main content

Hello Community,

We have a scenario where a Shop Order with a lot size of 100 pcs is scheduled using APB.
For Operation 10, all 100 pcs are planned to be completed in 21 hours.
Considering an 8-hour workday, the operation 10 would take roughly 3 days to complete.

My question is: Where in IFS Cloud can we see the per-day planned quantity for such operations?
I am looking for a way to monitor the breakdown (e.g., daily planned output) instead of only seeing the total planned hours or duration for the operation.

Any guidance, best practices, or navigation tips would be highly appreciated.

 

@Björn Hultgren ​@matt.watters would appreciate your input.

@Abdul the only thing that comes to mind is somehow using the Takt Time for this order/part/operation. Been a long time since I looked at Production Line Management with shop orders, but that’s all I can think of for now.


Hi ​@Tharindu Illangasinghe , have you come across such requirement ever or any idea how can we get such information.


Hi ​@Abdul,

 

Think the below window would be a good starting point. There you can see the hours that are needed for a particular operation in a given day. 

 

Perhaps you can add a column there to calculate the Planned Qty based on the Planned Hours in the day. 


Hi ​@Abdul,

 

Think the below window would be a good starting point. There you can see the hours that are needed for a particular operation in a given day. 

 

Perhaps you can add a column there to calculate the Planned Qty based on the Planned Hours in the day. 

Hi ​@Tharindu Illangasinghe,

Good suggestions. I will try this and will come back.