We have a scenario where a Shop Order with a lot size of 100 pcs is scheduled using APB.
For Operation 10, all 100 pcs are planned to be completed in 21 hours.
Considering an 8-hour workday, the operation 10 would take roughly 3 days to complete.
My question is: Where in IFS Cloud can we see the per-day planned quantity for such operations?
I am looking for a way to monitor the breakdown (e.g., daily planned output) instead of only seeing the total planned hours or duration for the operation.
Any guidance, best practices, or navigation tips would be highly appreciated.