Skip to main content
Question

Unfinished Activity Items – Vouchers have not been updated to GL

  • August 27, 2021
  • 2 replies
  • 131 views

Forum|alt.badge.img+2

We have problem with closing the Project Activity. In the Unfinished Activity Items we have message: “There are transactions that are posted and which have not been updated to General Ledger.” I checked the vouchers from the list – they have been updated to GL. How can we fixed the problem and close the Activity?

This topic has been closed for replies.

2 replies

Bhanuka Ranaweera
Hero (Employee)
Forum|alt.badge.img+9

Hello Agata,

 

A possible cause for the reported issue can be the project connections not being refreshed. Have you tried Refreshing the project connections and then try to close the activity?

 


Forum|alt.badge.img+2
  • Author
  • Do Gooder
  • 1 reply
  • August 27, 2021

Hello Agata,

 

A possible cause for the reported issue can be the project connections not being refreshed. Have you tried Refreshing the project connections and then try to close the activity?

 

I have refreshed Project connections but it didn`t help. I have checked vouchers lines which are on the list on the Unfinished Activity Items. I can`t find them on the Activity Connections Tab.