We have problem with closing the Project Activity. In the Unfinished Activity Items we have message: “There are transactions that are posted and which have not been updated to General Ledger.” I checked the vouchers from the list – they have been updated to GL. How can we fixed the problem and close the Activity?

Hello Agata,

 

A possible cause for the reported issue can be the project connections not being refreshed. Have you tried Refreshing the project connections and then try to close the activity?

 


Hello Agata,

 

A possible cause for the reported issue can be the project connections not being refreshed. Have you tried Refreshing the project connections and then try to close the activity?

 

I have refreshed Project connections but it didn`t help. I have checked vouchers lines which are on the list on the Unfinished Activity Items. I can`t find them on the Activity Connections Tab.