Sub-project exclusion from Earned value calculation

  • October 21, 2021
  • 1 reply
  • 124 views

Ushan Senarath
Hero (Employee)
Forum|alt.badge.img+11

In which scenario sub project is excluded from the Earned value calculation?

Best answer by Thilan Lasitha

Earned Value = Activity ProgressPlanned or Baseline value (To which value to be fetched in order to calculate the Earned value is decided on the option we give when creating the Baseline) 

 

If a Baseline has not been created, the system will always fetch the Planned value to calculate the Earned Value. 

 

There will always be an earned value in a Sub Project or in an Activity as long as there is Activity Progress and Baseline/Planned Cost. 

 

If we give 'Planned' for Earned Value Method when creating the Baseline and if there isn't any Planned cost for the Activity, there will not be an Earned Value for that Activity even though there is a progress in the Activity. 

Hope explanation will help on you !

 

View original
Did this topic help you find an answer to your question?
This topic has been closed for comments

Forum|alt.badge.img+8

Earned Value = Activity ProgressPlanned or Baseline value (To which value to be fetched in order to calculate the Earned value is decided on the option we give when creating the Baseline) 

 

If a Baseline has not been created, the system will always fetch the Planned value to calculate the Earned Value. 

 

There will always be an earned value in a Sub Project or in an Activity as long as there is Activity Progress and Baseline/Planned Cost. 

 

If we give 'Planned' for Earned Value Method when creating the Baseline and if there isn't any Planned cost for the Activity, there will not be an Earned Value for that Activity even though there is a progress in the Activity. 

Hope explanation will help on you !

 