Solved

Sub MS Receipts

  • 3 July 2023
  • 3 replies
  • 44 views

Userlevel 2
Badge +5

Hi,

 

What is the purpose served by the data in the tab Sub MS Receipts in MS L1 part?  How are the records created in this tab? the dates doesn’t have intervals either. pls can someone explain ?

 

Thanks in advance !

Yashodha 

icon

Best answer by Richard Owen 5 July 2023, 17:43

View original

3 replies

Userlevel 5
Badge +12

Hi Yash,

My understanding is that this tab will show data from the Master Schedule Grid<tab> but only where there are values in the Master Production Schedule field.

I hope that this helps! 

Userlevel 2
Badge +5

Hi Richard,

 

Thanks for the reply !

After doing some more testing around we found that the MS planned Due Date is actually when the Forecast cross the DFT and MPS get fixed. As per the MS planned Start Date, it dynamically calculates the cumaltive lead times (does not check the inventory part record data for lead times !)  That’s why I was confused about the time interval. Also if the MS part has a fixed lot size, there will be multiple records with the same MS planned Start Date and MS planned Due date :)

 

Kind Regards

Yash

Userlevel 5
Badge +12

Thanks for the additional information, much appreciated!

Reply