Shop Order Subcontract PO Receiving Error

  • May 9, 2025
  • 2 replies
  • 32 views

Forum|alt.badge.img+16
  • Hero (Customer)
  • 671 replies

Community,

 

What will be the issue that prevent the shop order sub contract job from being received? any idea?thank you.

 

2 replies

ww2sys
Do Gooder (Partner)
Forum|alt.badge.img+2
  • Do Gooder (Partner)
  • 9 replies
  • May 9, 2025

You have to Ship WIP to Supplier.  This is done on various screens including Shop Order, Report Shop Order Operation, Report Work Center Operation, Shop Floor Workbench, Disposition Shop Order, and Shop Order Operations.

If the outside operation backflush option is set to Purchase Order Arrival and the pegged purchase order is released, I believe the Ship WIP to Supplier is done automatically as part of Register Arrival.


Forum|alt.badge.img+16
  • Author
  • Hero (Customer)
  • 671 replies
  • May 9, 2025

@ww2sys Thank you for your reply.

Yes, we realized the missing steps.