Skip to main content

Hello,

I would like to split the operations within a work center across multiple resources. However, when I try to do this, I can’t set the quantity on the main work center (parent) to zero—it requires a value, even if it's not meaningful.

Do you know how to solve this? Or could you suggest the proper way to assign operations to individual machines (resources) within the same work center?

 

 

If you are not going to produce any quantity of the operation on the original operation I would suggest that you first change the operation to another work center that you actually will perform it at, and then split the quantity among the operations that will perform it. 


Thank you


Reply